Search Results for

    Show / Hide Table of Contents

    Calculate Actual Procurement Delays

    The actual delay is calculated according to the same logic for all procurement channels. An actual delay occurs when the line in the Project Processing Procurement page has the following settings:

    • Procurement Finish Date < Today
    • Posted quantity < Quantity
    • Procurement Status = <blank>, Planning, Released

    Feedback
    Senden Sie Feedback für diese Seite . (Beachten Sie, dass diese Umfrage auf Englisch ist.)

    In This Article
    Back to top 2025 © COSMO CONSULT - Data protection - Imprint