Search Results for

    Show / Hide Table of Contents

    Permanently Deferred in Sequence Planning

    With this function, you can defer production order lines in sequence planning permanently so that the re-scheduling process does not consider the production order line.

    To defer a production order in the Sequence Planning page, select the Permanently Deferred checkbox on the relevant line.

    The marked production order line is not re-scheduled even if the Schedule Deferred Prod. Order Lines toggle is turned on in the Priority Sequence Planning batch job (see Priority Planning) or the Sequence Pl. Start Advanced batch job (see Actions Menu).


    Feedback
    Submit feedback for this page .

    In This Article
    Back to top 2025 © COSMO CONSULT - Data protection - Imprint