    Calculate Actual Procurement Delays

    The actual delay is calculated according to the same logic for all procurement channels. An actual delay occurs when the line in the Project Processing Procurement page has the following settings:

    • Procurement Finish Date < Today
    • Posted quantity < Quantity
    • Procurement Status = <blank>, Planning, Released