Procurement Release
After the planning process is complete, procurement WBS positions with a status of Planning can be released by choosing Procurement > Release on the Project Planning and Processing page.
Released procurement documents can be created during the release process. Created documents are displayed per procurement channel.
Rolling Calculation after Procurement Release
Values from released procurement lines are displayed in the Total Direct Cost Released (LCY) field on the Project Rolling Calculation page.
Released amounts in procurement documents can vary from calculated values for any of the following reasons:
- Release is not complete.
- Released value is higher than calculated.
- Procurement Direct Unit Cost is different in procurement lines and calculation lines.
- Procurement values are moved to other WBS positions (Summarize Position).