Planning Flexibility in Sequence Planning
To ensure that production orders are not considered by the planning system and not recalculated if they have been moved in the sequence, and therefore have had their start- and end dates changed, turn on the No Plan. Flex. on Seq. Plan. toggle on the Planning Extension Setup page.
This setting will automatically set the Planning Flexibility field to None on the sequence planned production order lines during the scheduling process.