Navigation
As a graphical interface that shows maintenance order information, the Graphical Maintenance Scheduling page allows you to quickly change to different dates and time periods, search for specific tasks, change the appearance of the page, and view the maintenance order information using a Gantt chart.
This section provides an overview of how to navigate this page, change settings, and so on.
Go to Date
The Go to Date field allows you to move to a specific date in the chart.
Zoom to ...
Just below the Go to Date field is the Zoom to ... drop-down, which allows you to change the view to different time periods. The options are Month, Week, Day, Half Day, Hour, Half Hour, and Minute.
Search through Tasks
Next you can search through work centers or maintenance/production orders. This is a free text field so you can enter full or partial names of work centers or maintenance/production orders and then press Enter or choose the Search button to find all work centers or tasks with the search criteria. The filtered entries can be cleared by choosing the Clear button.
Chart Layout
The left pane shows the work centers and related maintenance orders and the right pane shows the corresponding work center workload (e.g., green = capacity available and red = capacity overload) as well as the related scheduled maintenance/production orders below (colors can be used to differentiate between maintenance orders with and without production orders as well as breakdown orders, orders for tools/inserts, and orders for non-sequence work centers).
For information about working in the Graphical Maintenance Scheduling page, see Usage.
Resource Charts
Below the chart are the Resource charts options, which determine what capacity information is shown in the chart. Both are described below:
- Free – No filtering, all capacity usage is displayed.
- Used – Shows only the times in which capacities are not available for planning.
- Errors - Shows only the capacities that have overloads.
- Available - Shows only the times is which capacities are available for planning.
Context Menus
On both sides of the chart, context menus can be opened to provide additional information about the work center or maintenance order. Tap and hold (or right-click) the work center or maintenance/production order to open the context menu.
For the work centers:
- The Planning Pool menu item opens the Planning Pool entries for this sequence work center.
- The Work Center Card menu item opens the related work center card.
- The Sequence Planning menu item opens the Sequence Planning page filtered on the selected sequence work center.
- The Capacity Ledger Entries, Planning Dimensions, Comments, Load, Statistics menu items opens the relevant pages for the selected work center.
- The Schedule menu item opens the Sequence Pl. Start Advanced dialog box, which will schedule the entries of the selected sequence work center.
- The Maintenance-/Setup menu item opens another menu that allow you to perform the standard maintenance-/order functions from Sequence Planning.
- The Optimize Planning menu item opens another menu that allow you to perform the standard priority planning and setup optimization functions from Sequence Planning.
For detailed information about these menu items, see Planning Pool & Sequence Planning in the COSMO Process Manufacturing content.
For the maintenance orders without production order:
The Maintenance Order Card menu item opens the related maintenance order.
The Post menu item opens a dialog for you to choose whether to post the selected maintenance order.
The Create Production Order menu item opens the Create Prod. Order from Maint. request form to create a production order from the maintenance order.
Note
Maintenance Orders from Work Centers with Work Center Type = Insert or Tool do not have the Create Production Order menu item.
For the maintenance orders with production order:
- The Maintenance Order Card menu item opens the related maintenance order.
- The Post menu item opens a dialog for you to choose whether to post the selected maintenance order.
- The Production Order Card menu item opens the related production order.
- The Graphical Prod. Order Planning menu item opens the Graphical Prod. Order Planning page where you can visually see the selected production order and its structures.
- The Graphical Sequence Planning menu item opens the Graphical Sequence Planning page that provides an overview of the related sequence work center with all related production orders. Double-tapping (or double-clicking) a production order in the left pane refocuses the right pane to the starting date of the production order.
- The Graphical Operation Scheduling menu item opens the Graphical Operation Scheduling page where you can visually see the selected production order.
For detailed information about these menu items, see Plant Maintenance, Graphical Prod. Order Planning, Graphical Sequence Planning, and Graphical Operation Scheduling.
Tooltips
To view a tooltip, tap (or hover over) an entry. For the maintenance orders, the tooltips show the maintenance order information including number, machine number, description, serial number, status, and the last maintenance date. For the production orders, the tooltips show the noted maintenance information as well as production order number, status, and job type number.
Chart Changes
The bottom of the page contains controls that allow you to change the appearance of the chart.
Expand/Collapse all rows
The first two icons allow you to either Expand all rows or Collapse all rows in the left pane of the chart.
Zoom In/Zoom Out/Zoom to fit into page
The third and fourth icons allow you to zoom into or out of the time periods in the right pane of the chart. The fifth icon allows you reset to a month view that will fit into the page.
Displays menu to choose visible columns
The sixth icon allows you to add columns to the chart area. This is especially useful because you can add Start and End Times for the production orders, as well as other production-related information.
Language
The Language drop-down allows you to change the information on the pages to English, German, French, Spanish, and Hungarian.
Style
The Style drop-down allows you to change the color of the chart area, including text, as well as the control icons at the bottom of the page.
Note
The custom option works with the TreeGrid CSS defined with EJS TreeGrid 16.1.2.
Gantt
The Gantt drop-down allows you to change the color of the Gantt area of the chart.
Note
The custom option works with the TreeGrid CSS defined with EJS TreeGrid 16.1.2.
Size
The Size drop-down allows you to change the size (height) of the rows in the chart area.
Scale
The Scale drop-down allows you to change the size of the chart area.
Contrast
The Contrast drop-down allows you to change the contrast between the foreground and background of the chart area.