Projects Setup
The general setup for COSMO Project Manufacturing is entered in the Projects Setup page, accessed using Tell Me. Choose the icon, enter Projects Setup, and then choose the related link.
Note
Although the Project Setup Wizard provides many default settings, there are additional fields that may need to be set up in the Projects Setup page. The default settings can also be reviewed and changed in this page.
General FastTab
The fields on this FastTab display general information about COSMO Project Manufacturing and are described in the following table.
Field | Description |
---|---|
Automatic Update Project Item Cost | Determines if the Update Project Item Cost batch job starts automatically with the Adjust Cost - Item Entries batch job. |
Default Project Posting Group | Indicates the Project Posting Group that will be defaulted to the Project Card each time a Project is created. The Default Project Posting Group from Project Types will overwrite the value in the Project Card, if it is set. For more information, see Project Posting Groups. |
Numbering FastTab
On this FastTab, number series needed in COSMO Project Manufacturing can be assigned.
Project FastTab
On this FastTab, the default fields for the Project Card are configured. Each field is described in the following table.
Field Group | Field | Description |
---|---|---|
Presets General | Project Version Start | Initializes the format for project versions. Each new project is marked as a first version. |
New Version per Status Change | Prompts for a new project version when a project status changes. The options are: - Never: Option will never be used - Question: Option will be used on request - Always: Option will always be used |
|
Presets Planning | Default Sales Code | Identifies the Sales Code that will be used as the default for all new projects. |
Default Unit of Measure Code | Controls which Unit of Measure is used in calculation lines as a default. The options are Base Unit of Measure, Sales Unit of Measure, and Purchase Unit of Measure. | |
WBS Format | Determines how WBS positions are formatted in the project structure. The options are: - Without Level 1: no WBS code will be created for level 1. Numbering is starting with level 2. - Components only: WBS codes are only created for lines with components (resources, items, resources, work/machine centers, and general components). |
|
Realized % (Base) | Used to automatically calculate the Realized % field. The options are: - Quantity: Posted / calculated quantity - Cost: Posted / calculated cost This can also be set up by using the field on a component (with higher priority). |
|
Location for Inv. Requests | Identifies the default location for inventory request related procurement planning. | |
Location for Purchase | Identifies the default location for purchase related procurement planning. | |
Procurement Planning Required | Determines if the planning and release of a procurement process is mandatory. The value in this field defaults to the Project Card if one is not defined in the Project Types Setup. | |
Project Dimensions | Project Dimension | Defines the dimension for automatically generated default dimension values for the Project No. field. |
Autom. Project Dimension | Determines if the dimension value should be inherited from the Project No. of the current project or from the main project. | |
Project Type Dimension | Allocates the dimension depending on the project type. The default dimension values are assigned in the Project Types Setup page. |
|
Dim. from Person Responsible | Determines if default dimensions from the person responsible are copied to the project. | |
Copy Dimension to Purchase | Determines if project dimensions are copied to the document dimensions in purchase documents. | |
Copy Dimension to Sales | Determines if project dimensions are copied to the document dimensions in sales documents. | |
Project Line Dimensions | Project Line Dimension 1 - 3 | Project line dimensions should be used if the dimensions are dependent on the project structure; that is, structure line dimensions are inherited by the upper structure. In addition to defining a single dimension for the project structure, it is possible to differentiate three dimensions on the project lines. The following rules apply for the use of dimensions on the project line: 1. The project line dimension is taken over from the component in the project line as a default value. 2. The project line dimension is extracted from a higher level, if no dimensions are attached to the individual component. 3. An alteration of a project line dimension results to a subsequent alteration within the sub-structures. 4. In the process of downgrading the project line, the dimension value is taken over from the highest position. The dimensions are transferred from the project line to the document that is generated from this line. |
General Functions | Default WIP Basis | Indicates the WIP Basis that will be defaulted to the Project Card each time a Project is created. The options are Sales Code, WIP Position, and Project. For more information, see WIP Basis. |
Auto. Reverse WIP | Automatically reverses WIP when a project status is changed to Completed. The options are: - Never: Automatic reversal does not happen and no message opens. - Question: A message opens for you to confirm the WIP reversal. This message will only occur if WIP has been posted for the project. - Always: Automatic reversal happens without user confirmation. For more information about the Reverse WIP function, see Actions Menu. |
|
Change Sales Code After Posting | Determines if Sales Codes can be changed after posting to the project line. The options are: - Never: Sales Code cannot be changed - Question: Sales Code can be changed after confirmation - Always: Sales Code can be changed For more information, see Sales Codes |
Calculation FastTab
On this FastTab, all settings relating to Calculations are defined. Each field is described in the following table.
Field Group | Field | Description |
---|---|---|
General Presets | Purch. Disc. Reduce Unit Cost | Manages the cost calculation and therefore the valuation of a calculation line by using a Line Purchase Discount %. |
Set Budget with Sales Doc. | Determines if WBS positions are budgeted automatically during the creation of a sales document (quote or order). Changes in linked substructures have no effect on the sales value. |
|
Preset comments from extended text | Insert Sales Ext. Text | Determines if extended text descriptions from components (Services and Items) are copied into the Project Budget Sales page. These comments are available for review by turning on the Comment Sales toggle. |
Insert Purch. Ext. Text | Determines if extended text descriptions from components (Services and Items) are copied into the Project Planning and Processing page. These comments are available for review by turning on the Comment Procurement toggle. |
|
Update Rules | No New Calculation | Used when updating positions in the Project Budget Calculation page. If activated, turns on Do not recalculate toggle on the Project Line Update Rules request page and the following fields cannot be turned on. |
Replace Description | Used when updating positions in the Project Budget Calculation page. If activated, turns on the Replace description toggle on the Project Line Update Rules request page. |
|
Replace Comments | Used when updating positions in the Project Budget Calculation page. If activated, turns on the Replace comments toggle on the Project Line Update Rules request page. |
|
Replace Cost/Price | Used when updating positions in the Project Budget Calculation page. If activated, turns on the Replace units of measure and costs/prices toggle on the Project Line Update Rules request page. |
|
Set Quantity Zero | Used when updating positions in the Project Budget Calculation page. If activated, turns on the Set Quantity Zero toggle on the Project Line Update Rules request page. |
Planning FastTab
On this FastTab, all settings relating to Planning are defined. Each field is described in the following table.
Field Group | Field | Description |
---|---|---|
Persons Planning | Option Capacity | Defaults to the View Options FastTab in the Planning View Person page. Base Table: Capacity Ledger Entries |
Option Planning | Defaults to the View Options FastTab in the Planning View Person page. Base Table: Project Calendar Entries |
|
Option Simulation | Defaults to the View Options FastTab in the Planning View Person page. Base Table: Project Calendar Entries |
|
Option Available | Defaults to the View Options FastTab in the Planning View Person page. | |
Option Available % | Defaults to the View Options FastTab in the Planning View Person page. | |
Option Utilization % | Defaults to the View Options FastTab in the Planning View Person page. | |
Option Time Entry | Defaults to the View Options FastTab in the Planning View Person page. Base Table: Project Journal Lines |
|
Option Posted | Defaults to the View Options FastTab in the Planning View Person page. Base Table: Project Ledger Entries |
|
Budget Allocation / Forecast | Base Calendar Code | Used as the default person resources setup for calculating capacities. |
General Project Work-Hour Template | Used as the default person resources setup for calculating capacities. | |
Cash Flow Pmt. Code | Used as the default cash flow payment code that transfers to the Project Card for the Project Liquidity module integration in COSMO Project Manufacturing (see Project Liquidity Integration). | |
MSP Project Interface | MSP Path / MSP Import Comp. Type / MSP Import Comp. No. | See Microsoft Project Integration. |
Procurement FastTab
On this FastTab, all settings relating to Procurements are defined. Each field is described in the following table.
Field Group | Field | Description |
---|---|---|
General | Procurement Cost Source | Determines the pricing method for the Direct Unit Cost in the procurement process. |
Time Entry | Project Journal Time Entry | Identifies the default project journal templates for internal time entries. |
Terminal Posting Allowed | Determines if the person recording time can also post their time in the Terminal. | |
Purchase and Inventory | Post Released Quantity only | Determines if released procurement lines are set to Finished automatically when the procurement documents (purchase order, inventory request) are posted. With this option, it is possible to post up to the released quantity, and when that quantity is reached, the procurement lines will be closed. An error will occur if there is an attempt to post more than the release quantity. NOTE: This option cannot be used with unplanned travel expenses if it is not possible to release a quantity for an unplanned cost; therefore, use the Auto. Close Proc. Line field to handle automatic posting (see the next field). |
Auto. Close Proc. Line | Determines if released procurement lines are set to Finished automatically when the procurement documents (purchase order, inventory request) are posted. With this option, it is possible to post as much as needed with no limit to the released quantity. However, the procurement lines will be closed if the full released quantity or more are posted. NOTE: Only this option can be used with unplanned travel expenses because it is possible to post unplanned costs. |
|
Purchase | Req. Wksh. Template / Req. Wksh. Name | Identifies the template and name of the requisition worksheet; required to use the purchase procurement channel is used. |
External Services Code | Allows the use of resources on purchase documents using a link to a G/L account. | |
Order Confirmation Required | Determines if the Order Confirmation Required checkbox is selected in Purchase Documents. | |
Inventory | Project Journal Inventory Requests | Indicates the project journal to be used for inventory requests. |
Inv. Request per Location | Determines if multiple inventory requests will be created for a procurement covering several positions. | |
Populate Qty. in Inv. Requests | Determines if the picking amount will not be confirmed on order completion. | |
Check Quantity in Inv. Req. | Determines if an inventory audit of the respective storage location will be checked during posting. | |
Production | Def. Prod. Order Status | Determines the default production order to be used if production procurement is used. |
Reserve Inv. Request for Production Order | Determines if automatic reservations of production orders are made against inventory requests on job procurement release. For more information, see Production Orders. |
|
Dummy Routing Code | Specifies a dummy Routing Code used to directly create Procurement Production Orders from Project Lines with Routing-related lines (work centers/machine centers). | |
Dummy Prod. BOM Code | Specifies a dummy Production BOM Code used to directly create Procurement Production Orders from Project Lines with Component-related lines (items). The dummy Production BOM must have an empty Unit of Measure Code. To create the dummy production BOM, choose the ellipsis button or choose the Create Dummy Production BOM action on the Actions menu. |
|
Assembly | Reserve Inv. Request for Assembly Order | Determines if automatic reservations of assembly orders are made against inventory requests on project procurement release. For more information, see Assembly Orders. |
Sales FastTab
On this FastTab, the default presets fields for sales are configured.
Some fields on this FastTab offer the following three options:
- Never – Option will never be used
- Question – Option will be used on request
- Always – Option will always be used
The fields on the Sales FastTab are described in the following table.
Field | Description |
---|---|
New Version per Sales Quote | Prompts for a new job version when a sales quote is created. |
Set Project Status Quote | Automatically changes the status on the Project Card from Planning to Quote when a sales quote is created. |
Set Project Status Open | Automatically changes the status on the Project Card from Planning or Quote to Open if you create an order from an offer or if you directly create an order. |
Autom. Release Sales Order | Automatically releases the sales order on creation. |
Procurement with Sales Release | Automatically releases procurement on release of the order. |
Auto. Completion Reason Alternative Projects | Automatically completes an alternative project with this completion reason. |
Fixed Project Line Sales | Can be used to implement a function for automatic WBS finding in Sales Lines. For more information, see Fixed Project Lines Budget. |
Credit Warnings | Specifies whether a warning about the customer's credit status (credit limit or overdue balance) is shown when a customer is added to a Project Card. The options are Both Warnings, Credit Limit, Overdue Balance, and No Warning. |
Signals FastTab
This FastTab contains fields that are used with the Signal Monitor. The fields are described in the following table.
Field/Field Group | Description |
---|---|
Signal Monitor Tolerance % | Indicates a buffer for controlling differences in the Realized % field. |
Traffic Lights | Indicates the color options available to provide better visual displays. |
For more information, see Signal Monitor and Degree of Completion.
Actions Menu
The actions on the Actions menu are described in the following table.
Action | Description |
---|---|
Create Dummy Production BOM | Creates a certified dummy Production BOM without a Unit of Measure Code. This Production BOM is needed for the creation of Project Procurement Production Orders. |
Transfer Project Purchase Prices and Discounts | This action is available if the New sales pricing experience feature update has been enabled in Feature Management in Business Central 16.00 (or later), which transfers the existing Project Purchase Prices and Discounts to the new Price List table. Run this function to ensure proper pricing functionality in COSMO Project Manufacturing. Once run, the action is no longer available on the Projects Setup page. For more information about feature updates, see Microsoft Documentation. |
See Also
Project Card
Calculation and Budgeting
Sales Documents
Project Planning and Resource Planning
Project Processing
Project Controlling