    Tools in the Work Center Prod. Rate Card

    The values of a tool are copied to the Work Center Prod. Rate Card after their creation and can be maintained separately for every machine (work center).

    For information about the fields on the Tool/Insert FastTab, see Tool Management.

    Tool Time Calculations

    All times from the tool are calculated to the setup times and production rate values in the Work Center Prod. Rate Card using the following formulas:

    • Setup time = Ramp-up Time + Tool Setup Time
    • Production rate time = (Cavity * (Cycle Quantity / Cycle Time))

    Different time units will be converted.