Planning Processes Page
The Planning Processes page manages the processes for a job, which are derived from the calculation lines. The view contains the essential information for:
- work and duration
- predecessor / successor relationships
- restriction types
Note
This page will not contain any lines until the Planning Processes have been completed (see Job Process Planning and Scheduling).
In the Planning Processes page, a significant number of fields are populated with values from the Job Planning and Processing page. Therefore, the following table does not provide a complete description of each field.
Fields on the Planning Processes page
Field | Description |
---|---|
Planning Status | Indicates the current state of the WBS position. The options are Planning, Release, and Finished. |
Process ID | Indicates the unique process number assigned to the WBS position (see Process Logic). |
Predecessor ID | Creates links between process lines (see Process Logic). |
Predecessor / Follower | Indicates the hierarchical link between process lines (see Process Logic). |
Description | Defaults from the Job Planning and Processing page. |
Comment General | Indicates if a job comment line with Comment Type = General exists for the WBS position. |
Milestone | If selected, the WBS position is set for milestone processing. |
MSP Interface | Indicates a mapping to Microsoft Project (see Microsoft Project Integration). |
Work Quantity / Work Format | Identifies the amount of time to complete the WBS position. |
Duration Quantity / Duration Format | Identifies the length of time to complete the WBS position. |
Constraint Type / Constraint Date / Constraint Minutes | Affect the calculation of the start and end dates for the planning process (see Process Logic). |
Start | Indicates when processing for the WBS position is set to begin. |
Finish | Indicates when processing for the WBS position is set to end. |
Signal Conflicts / Signal Conflict | Indicates with symbols or letters if there is a conflict with dates or resource availability (see Detect Conflicts). |
Work Not Planned Hours | Displays the number of hours that have not been planned; that is, resources that have not yet been allocated (see Assign Planning Resources). |
Assigned Resource No. | Displays the resources that have been assigned to the WBS position (see Assign Planning Resources). |
Assigned Capacity % | Displays the total capacity percentage assigned to the WBS position (see Assign Planning Resources). |
Work Planned Hours | Displays the number of hours that have been planned; that is, resources have been allocated (see Assign Planning Resources). |
Effort driven | Controls if the process, start date or end date should be limited by their planned availabilities (see Calculation of Schedule Entries). |
Schedule Type | Determines how capacity is planned (see Scheduling and Schedule Types). |
Scheduled Hours | Displays how many hours have been scheduled for this planning process. |
Scheduled Freeze | If selected, planning for the WBS position is stopped regardless of the Schedule Type. The planned times for this position will not be changed during the planning process. |
% Complete | Indicates the current stage of completion for the WBS position. |
Process No. | Identifies the unique process number assigned to the process line. |
Outline Code | This field is not currently used. |
Type | Defaults from the Job Planning and Processing page. |
No. | Defaults from the Job Planning and Processing page. |
Work Type Code | Defaults from the Job Planning and Processing page. |
Quantity | Indicates how many units of the component should be planned. |
Unit of Measure Code | Defaults from the Job Planning and Processing page. |
Hours Fixed | Displays how many hours are planned for this position, with Scheduling Type = Fixed. |
Hours Planned | Displays how many hours are planned for this position, with Scheduling Type = Planned. |
Hours Simulated | Displays how many hours are planned for this position, with Scheduling Type = Simulated. |
Assigned Resources | Indicates if resources have been assigned to the WBS position (see Assign Planning Resources). |
Scheduled Early Start | Displays the earliest planning date for the process. |
Scheduled Early Days | Displays how many days are too early for real scheduling. |
Scheduled Late Finish | Displays the latest schedule for this process. |
Scheduled Late Days | Displays how many days are too late for real scheduling. |
Hours after Finish | Displays how many hours were designed after the scheduled end. |
Sorting No. | Creates a custom sort order for the WBS positions. |
Process Channel | Processes are created if the calculation position is linked with a process channel. The options are: - Work: Processes will be created with Work and Duration. - Lead time: Processes are created only with Duration. - Structure: Processes are created without Work and Duration. |
Person Responsible | Identifies a person (resource) that is responsible for the WBS position. |
Lead Time Calculation | Indicates the lead time calculation (for example, 2W for two weeks) to be used for planning a component. |
Priority Option | Indicates the level of importance of the WBS position. The options are None, Middle, High, Very high, and Top. |
Priority | Indicates a numeric level of importance of the WBS position. |
Deadline | Indicates a specific date when the WBS position must be completed. |
Process Type Fixed … | Specifies which base to fix in calculations. The options are Units (by planning resources), Work, and Duration. |
Work Overplanned Hours | Display how many hours were planned in excess; that is, too many planning resources have been assigned. |
Planned Capacity % | Identifies the assignment of planned capacity. 100% corresponds to one person. |
Early Start | Displays the earliest possible time of planning for the start of the process. |
Buffer Start Days | Indicates the number of days that can be used as a buffer for the starting date. |
Minutes before Start | Displays the time delay on the start date. |
Start Time | Displays the start time if start and end times are specified in planning for the WBS position. |
Late Start | Displays the last possible time of planning for the start of the process. |
Early Finish | Displays the earliest possible time of planning for the end of the process. |
Minutes at Finish | Displays the time offset at the end of the process to the end date. |
Finish Time | Displays the finish time if start and end times are specified in planning for the WBS position. |
Buffer Finish Days | Indicates the number of days that can be used as a buffer for the ending date. |
Late Finish | Displays the last possible time of planning for the end of the process. |
Summary Start | Displays the planned beginning date for a summary task. |
Summary Finish | Displays the planned ending date for a summary task. |
Signal Forward | Displays a signal if the planning direction is forward. |
Signal Backward | Displays a signal if the planning direction is backward. |
WBS | Defaults from the Job Planning and Processing page. |
Time Entry Hours | Indicates the number of hours that have been posted in the Time Entry Job Journal for the WBS position. |
Performed Hours | Indicates the number of hours posted as usage in the Project Ledger Entries. |
Action Bar
The action bar includes menus that contain actions specific to COSMO Project Manufacturing. The actions in each menu are described in the following table.
Menu | Action | Description |
---|---|---|
Delete | Deletes the selected process line. | |
New | New Process | Creates an entry in the hierarchical processing structure. For more information, see Job Process Planning and Scheduling. |
Home | Chain | Sets the link between predecessors and followers. |
Planning Setup | Opens the Job Planning Setup page, which is defaulted from Standard Planning Setup and can be changed for individual Job planning parameters. | |
Release | Releases a WBS position for planning processes. | |
Finish | Finishes the planning process for the WBS position. | |
Scheduling | Schedule Process / Schedule Processes | The following actions plan processes for WBS positions without calculating predecessors and successors: - Schedule Process - Schedule Simulated only For more information, see Calculation of Schedule Entries. |
Delete Schedule Entries | Deletes existing planning entries. | |
Resources | Resource Availability | Opens the Planning Res. Availability page, which displays availability for the resource in a matrix view (see Availability Overview). |
Resource Allocation | Opens the Planning Res. Allocation page, where resources can be assigned to WBS planning positions (see Resource Allocation). | |
MSP Interface | MS Project Import / MS Project Export / MSP Codes | These actions are used with the Microsoft Project integration. For more information about setting up these actions, see Microsoft Project Integration. |
Actions Menu
The actions on the Actions menu are described in the following table.
Menu | Action | Description |
---|---|---|
Structure | New Process ID | Recalculates Process IDs that are out of order due to inserted processes. For more information, see Job Process Planning and Scheduling. |
Sorting | Chance sorting / Up / Down | Changes the sorting of the lines: - Chance sorting: changes the sorting key from the WBS Position field to the Sorting No. field and vice versa. - Up - Down |
Schedule | Schedule Simulated only | Plans processes for WBS positions with Schedule Type = Simulated without calculating predecessors and successors. |
Schedule (with links) | Processes effort driven / Processes never effort driven | Plans processes for linked WBS positions: - Processes effort driven - Processes never effort driven For more information, see Calculation of Schedule Entries. |
Update Scheduling | Simulated to Planned / Fix all and release / Planned to Fixed / Fixed to Planned / Planned to Simulated | Updates the Schedule Type in the lines in the Job Scheduled Entries page: - Simulated to Planned: Changes the Schedule Type from Simulated to Planned in the scheduled lines. - Fix all and release: Changes the Schedule Type to Fixed and changes the status to Released in all scheduled lines. - Planned to Fixed: Changes the Schedule Type from Planned to Fixed in the scheduled lines. - Fixed to Planned: Changes the Schedule Type from Fixed to Planned in the scheduled lines. - Planned to Simulated: Changes the Schedule Type from Planned to Simulated in the scheduled lines. For more information, see Scheduling and Schedule Types. |
Related Menu
The actions on the Related menu are described in the following table.
Menu | Action | Description |
---|---|---|
Planning | Process Card | Opens the Job Process Card page, which provides a card view of all the information in the Planning Processes page for the selected WBS position. |
Job Team | Opens the Job Team page, which displays all planning resources assigned to the job. | |
MS Project | MSP Lines | Used with the Microsoft Project integration. For more information about setting up these actions, see Microsoft Project Integration. |
Graphical Extension | Graphical Resource Planning | Opens the Graphical Resource Planning page, which provides a graphical view of assigned resources relating to this job process. For more information, see Graphical Project Resource Planning. |
Graphical Project Planning | Opens the Graphical Project Planning page, which provides a graphical view of job line processes relating to this job. For more information, see Graphical Project Planning. |
Feedback
Submit feedback for this page .